You’ve picked a contractor and the contract is on the table. This is the moment that protects your money, your schedule and your home. A good contract is clear enough that you and your contractor read it the same way. This guide goes through it clause by clause, shows the red flags, and ends with a 10-minute check you can do before you sign.

Quick answer: Before signing a remodeling contract in Kirkland, make sure it has a detailed scope of work and a materials list, the full price with sales tax shown, a payment schedule tied to finished work, a start date and expected length, who gets the permits, a written change-order process, lien releases before final payment, and what “finished” means. In Washington, residential jobs of $1,000 or more also need a signed disclosure statement before work starts. Don’t sign a contract that’s vague, asks for a large payment up front, or lets changes happen “by phone”.

The contract, clause by clause

ClauseWhat it should sayRed flag
Who’s whoYour name and address; the contractor’s legal business name, address and Washington registration numberA name that doesn’t match the contractor’s L&I registration
Scope of workRoom by room: what’s removed, built and installed, with drawings attached; what’s not included“Remodel kitchen as discussed”
MaterialsBrand, model, color or grade for main items“Standard” or “builder grade” with no details
AllowancesA dollar amount for items you’ll choose later, and whether it includes installationVery low allowances that make the price look cheaper
PriceThe total, what it includes, and sales tax shownA price with no breakdown, or no mention of tax
PaymentsPayments tied to finished stages of work, with a final payment held until the job is completeA large deposit, cash only, or payment to a person’s name
ScheduleA start window, expected length, and how delays will be explainedNo dates at all
PermitsWho applies, who pays the fees, and that work waits for the permit“You don’t need a permit for this” on structural, plumbing or electrical work
Change ordersEvery change in writing, with price and time, signed before work“We’ll sort out extras at the end”
Subcontractors and liensMain subcontractors and suppliers listed; lien releases before final paymentNo mention of lien releases
Insurance and damageThe contractor’s liability insurance covers damage to your homeNo proof of insurance
Site rulesWork hours, cleanup, dust protection, parking and where materials are storedNothing about cleanup or protection
FinishingWhat “complete” means: final inspection passed, punch list done, documents handed overNo definition of done
After the jobHow to report a problem after completion, and how fast it will be looked atNo process at all
Ending the contractWhen either side can end it, and how work done so far is paid forOnly the contractor can end it
DisputesSteps to follow: talk, then mediation, then arbitration or courtA clause you don’t understand, or that you didn’t notice
A contractor and homeowner going over plans before signing
A contractor and homeowner going over plans before signing. Read every clause together so you both understand it the same way.

The four clauses that matter most

1. Scope of work: the heart of the contract

A common source of trouble is “I thought that was included.” A good scope lists the work room by room. It says what’s being removed, what’s being built, and what’s not included, like painting other rooms or moving the washer. Drawings and a materials list should be attached and named in the contract.

Ask for: “Please attach the plans and the full materials list, and add a list of what’s excluded.”

Plans and material samples on a kitchen counter
Plans and material samples on a kitchen counter. Drawings and a materials list should be attached to the contract.

2. Payment schedule: pay for work that’s done

Washington L&I’s advice is simple: don’t pay in full until the job is done. Be careful of contractors who want only cash, large deposits, or the whole price up front (L&I). Each payment should match a stage you can see, like passed inspections or installed cabinets.

Washington’s disclosure statement also reminds you that you can hold back part of the payment, called retainage, for your protection (RCW 18.27.114).

3. Change orders: no surprises on the bill

A change order is a short written agreement that changes the contract. Each one should say:

  • what’s changing and why
  • the added or reduced cost
  • the effect on the schedule
  • that both of you signed it before the work is done

Ask for: “No extra work without a signed change order.”

4. Lien releases: protect your home

If your contractor doesn’t pay a subcontractor or supplier, they can put a lien (a legal claim) on your home, even if you already paid the contractor. As the owner, you’re ultimately responsible for making sure suppliers, subcontractors and workers are paid (L&I). A lien release is a signed note from a subcontractor or supplier saying they’ve been paid.

Ask for: “Lien releases from all subcontractors and suppliers before the final payment.”

Washington and Kirkland rules to know

  • The disclosure statement. For residential work of $1,000 or more, the contractor must give you a disclosure statement to sign before starting work. It shows their registration number and bond amount, warns that unpaid suppliers or subcontractors can lien your property, and tells you that you can ask for lien releases (RCW 18.27.114).
  • Sales tax. In Washington, remodeling for a homeowner is generally subject to sales tax on the total charge, including labor, materials and permits (WA Department of Revenue). Make sure the contract shows it.
  • Permits. Your contractor should get the permits. For how long Kirkland review takes, see our Kirkland renovation planning guide.
  • Kirkland business license. Kirkland requires a city business license for businesses working in the city, including those based elsewhere (WA Department of Revenue).
  • Canceling a contract signed at home. If you signed after a sales visit to your home, the FTC Cooling-Off Rule may let you cancel until midnight of the third business day. Some sales are exempt, so check the cancellation notice (FTC).

A worked example: a payment schedule for a $60,000 kitchen

This is a made-up example to show a fair structure. It isn’t a rule, a real project or a quote.

PaymentWhenAmount
1At signing$6,000 (10%)
2Demolition done and rough plumbing and electrical inspections passed$15,000
3Drywall done and cabinets installed$18,000
4Counters, fixtures and appliances installed$15,000
5Final inspection passed, punch list done, lien releases received$6,000 (10%)
Total$60,000

Each payment comes after work you can see, and the last one waits until everything is truly finished. For typical kitchen prices, see our kitchen remodel cost guide.

A kitchen island being built during a Kirkland remodel
A kitchen island being built during a Kirkland remodel. Tie each payment to a stage of work you can see, like cabinets installed.

Before you sign: your 10-minute check

  • The contractor’s name matches their registration on L&I Verify
  • The scope is room by room, with drawings and a materials list attached
  • Exclusions are listed
  • Allowance amounts are realistic and say whether installation is included
  • The price shows sales tax
  • Payments follow finished work, and the last payment waits for final inspection and lien releases
  • Start date, expected length and permit responsibility are written down
  • The change-order process requires signed, priced changes before work
  • “Complete” is defined, and there’s a way to report problems after the job
  • You’ve received, or been promised, the disclosure statement before work starts

Still choosing a contractor? Start with our Kirkland renovation due-diligence checklist.

A finished modern kitchen in a Kirkland home
A finished modern kitchen in a Kirkland home. A clear contract makes it easier to get to a finished room like this.

How CHC Remodel handles contracts

At CHC Remodel, scope changes are confirmed in writing, with any cost or schedule impact, before work goes ahead. We’re happy to walk through our contract with you line by line before you sign. See our remodeling process and our Kirkland remodeling services, browse project photos on our Houzz profile, or read what homeowners say in our Google reviews. WA contractor registration CONTEHC837KA.

This article is general information, not legal advice for your situation. Contract terms and rules can change, so consider having a Washington attorney review a large contract before you sign.

Frequently asked questions

What should a remodeling contract include?

Names and the contractor’s registration number, a detailed scope, materials, allowances, the price with tax, a payment schedule, dates, permits, a change-order process, lien releases, site rules, what “finished” means, and how disputes are handled.

How much should I pay when I sign?

L&I doesn’t give one fixed amount, but it warns against large deposits and paying in full before the job is done. Keep payments tied to finished work.

What is a change order?

A short written agreement that changes the contract. It lists the change, the cost and the time it adds, and both of you sign it before the work is done.

What is a lien release, and why do I need one?

It’s a signed note from a subcontractor or supplier confirming they’ve been paid. Without one, an unpaid sub or supplier could put a lien on your home, even if you paid your contractor.

Can I cancel a remodeling contract after signing?

If you signed after a sales visit at your home, the FTC Cooling-Off Rule may give you three business days to cancel. Otherwise, the contract’s own terms apply, so read the termination clause.

Should a lawyer review my contract?

For a large project, or any clause you don’t understand, a short review by a Washington attorney is a reasonable cost compared with the size of the job.

Verified Credentials

WA L&I registration

CONTEHC837KA

★★★★★ 80+ five-star Google reviews
250+ reviews across other directories

Contemporary Home Construction, LLC (CHC Remodel). Look us up with the same free state tool this checklist recommends.

siamak

Siamak Firooz is a structural engineer and CEO of CHC Remodeling, where he leads a team focused on delivering high-quality, value-driven construction. With a Master’s degree in engineering and years of experience consulting on residential and commercial projects, he brings technical expertise and strategic oversight to every job.